Roadmaps and Timeframes

We’re committed to providing clear, consistent, and predictable timelines for all building and land development projects. This page outlines our standard process timeframes and roadmaps; from application submission to project completion; so that developers, property owners, and community members can understand what to expect at every stage. Our goal is to support responsible growth, improve transparency, and help you plan with confidence.

  • The development process roadmaps are designed to provide clear, step-by-step visibility into each stage of plan review and approval. By outlining timelines, key milestones, and responsibilities, these roadmaps help customers understand what to expect, prepare more effectively, and navigate the process with confidence. This transparency ensures smoother collaboration between applicants, reviewers, and the community.

    Building Permit Submission Process

    Site Plan Submission Process - Future Development

  • These Timeframes are as of ENTER DATE HERE, timeframes are subject to change. 

    Building Development
    Plan Type Time for 1st Review Time for Subsequent
    Reviews/Resubs    
    New Commercial Plan N/S 4 Weeks/20 Bus. Days 2 Weeks/10 Bus. Days
    Tenant Layout Plan TLO 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days
    Alteration & Repair Alt/Rep 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days
    After issuance of permit; All Revisions for N/S + TLO + Alt / Rep are 5 business days
    Targeted    
    New Commercial Plan 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days
    Tenant Layout Plan 1 Week /5 Bus. Days 1 Week /5 Bus. Days
    Alteration/Repair Plan 1 Week /5 Bus. Days 1 Week /5 Bus. Days
    Targeted Projects: After issuance of permits, all Revisions for N/S + TLO +Alt/Rep are 5 bus. Days
    Structures Other than Buildings    
    Retaining Walls, Ramps,
    Elevators, Site Lights,
    new Antenna Towers, etc.
    2 Weeks/10 Bus. Days 1 Week /5 Bus. Days
    Signs, Antennas added
    to existing Towers
    1 Week /5 Bus. Days 1 Week /5 Bus. Days
    Residential    
    Single family Homes (additions etc.) 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days
    Priority Reviews (waived plans) 1 Week /5 Bus. Days 1 Week /5 Bus. Days
  • Land Development
    Sketch Plans Minor Plans Preliminary Plans
    Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days
    QC Review: 3 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days
    Intake 1st Submisson Processing: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days
    1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days
    1st Submission: 8 Bus. Days 1st Submission: 14 Bus. Days 1st Submission: 12 Bus. Days
      Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 3 Bus. Days
      2nd Submission: 10 Bus. Days 2nd Submission: 8 Bus. Days
    Expedited Review Plans (Targeted) Final Plans Administrative Review Plans
    Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days
    QC Review: 3 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days
    Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson Processing: 2 Bus. Days
    1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days
    1st Submission: 17 Bus. Days 1st Submission: 27 Bus. Days 1st Submission: 14 Bus. Days
    Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 2 Bus. Days  
    2nd Submission: 12 Bus. Days 2nd Submission: 17 Bus. Days  
    Intake 3rd Submisson: 2 Bus. Days Intake 3rd Submisson: 2 Bus. Days  
    3rd Submission: 8 Bus. Days 3rd Submission: 8 Bus. Days  
    Revisions - Preliminary Plans Priority Plans Revisions - Final Plans
    Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days
    QC Review: 3 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days
    Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days
    1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days
    1st Submission: 10 Bus. Days 1st Submission: 27 Bus. Days 1st Submission: 15 Bus. Days
    Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 2 Bus. Days
    2nd Submission: 7 Bus. Days 2nd Submission: 17 Bus. Days 2nd Submission: 10 Bus. Days
    Intake 3rd Submisson: 2 Bus. Days Intake 3rd Submisson: 2 Bus. Days Intake 3rd Submisson: 2 Bus. Days
    3rd Submission: 8 Bus. Days* 3rd Submission: 8 Bus. Days* 3rd Submission: 8 Bus. Days*
    Early Grading Plans County Attorney Review Signature Submission (All applicable case types)
    Intake QC Processing: 2 Bus. Days Intake Processing/Routing: 2 Bus. Days Intake Processing/Routing: 2 Bus. Days
    QC Review: 3 Bus. Days 1st Submission: 10 Bus. Days 1st Submission: 5 Bus. Days
    Intake 1st Submisson: 2 Bus. Days 1st Submission (Family land transfer and Res. Deed of Consolitdation): 20 Bus. Days  
    1st Submission Routing: 2 Bus. Days    
    1st Submission: 15 Bus. Days    
    Plats/Simple/Resub./Consol.    
    Intake QC Processing: 2 Bus. Days    
    QC Review: 3 Bus. Days    
    Intake 1st Submisson: 2 Bus. Days    
    1st Submission Routing: 2 Bus. Days    
    1st Submission: 12 Bus. Days    
    Intake 2nd Submisson: 2 Bus. Days    
    2nd Submission: 8 Bus. Days