Roadmaps and Timeframes
We’re committed to providing clear, consistent, and predictable timelines for all building and land development projects. This page outlines our standard process timeframes and roadmaps; from application submission to project completion; so that developers, property owners, and community members can understand what to expect at every stage. Our goal is to support responsible growth, improve transparency, and help you plan with confidence.
The development process roadmaps are designed to provide clear, step-by-step visibility into each stage of plan review and approval. By outlining timelines, key milestones, and responsibilities, these roadmaps help customers understand what to expect, prepare more effectively, and navigate the process with confidence. This transparency ensures smoother collaboration between applicants, reviewers, and the community.
Building Permit Submission Process
Site Plan Submission Process - Future Development
These Timeframes are as of ENTER DATE HERE, timeframes are subject to change.
Building Development Plan Type Time for 1st Review Time for Subsequent Reviews/Resubs New Commercial Plan N/S 4 Weeks/20 Bus. Days 2 Weeks/10 Bus. Days Tenant Layout Plan TLO 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days Alteration & Repair Alt/Rep 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days After issuance of permit; All Revisions for N/S + TLO + Alt / Rep are 5 business days Targeted New Commercial Plan 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days Tenant Layout Plan 1 Week /5 Bus. Days 1 Week /5 Bus. Days Alteration/Repair Plan 1 Week /5 Bus. Days 1 Week /5 Bus. Days Targeted Projects: After issuance of permits, all Revisions for N/S + TLO +Alt/Rep are 5 bus. Days Structures Other than Buildings Retaining Walls, Ramps,
Elevators, Site Lights,
new Antenna Towers, etc.2 Weeks/10 Bus. Days 1 Week /5 Bus. Days Signs, Antennas added
to existing Towers1 Week /5 Bus. Days 1 Week /5 Bus. Days Residential Single family Homes (additions etc.) 2 Weeks/10 Bus. Days 1 Week /5 Bus. Days Priority Reviews (waived plans) 1 Week /5 Bus. Days 1 Week /5 Bus. Days Land Development Sketch Plans Minor Plans Preliminary Plans Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days Intake 1st Submisson Processing: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission: 8 Bus. Days 1st Submission: 14 Bus. Days 1st Submission: 12 Bus. Days Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 3 Bus. Days 2nd Submission: 10 Bus. Days 2nd Submission: 8 Bus. Days Expedited Review Plans (Targeted) Final Plans Administrative Review Plans Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson Processing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission: 17 Bus. Days 1st Submission: 27 Bus. Days 1st Submission: 14 Bus. Days Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 2 Bus. Days 2nd Submission: 12 Bus. Days 2nd Submission: 17 Bus. Days Intake 3rd Submisson: 2 Bus. Days Intake 3rd Submisson: 2 Bus. Days 3rd Submission: 8 Bus. Days 3rd Submission: 8 Bus. Days Revisions - Preliminary Plans Priority Plans Revisions - Final Plans Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days Intake QC Processing: 2 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days QC Review: 3 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days Intake 1st Submisson: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission: 10 Bus. Days 1st Submission: 27 Bus. Days 1st Submission: 15 Bus. Days Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 2 Bus. Days Intake 2nd Submisson: 2 Bus. Days 2nd Submission: 7 Bus. Days 2nd Submission: 17 Bus. Days 2nd Submission: 10 Bus. Days Intake 3rd Submisson: 2 Bus. Days Intake 3rd Submisson: 2 Bus. Days Intake 3rd Submisson: 2 Bus. Days 3rd Submission: 8 Bus. Days* 3rd Submission: 8 Bus. Days* 3rd Submission: 8 Bus. Days* Early Grading Plans County Attorney Review Signature Submission (All applicable case types) Intake QC Processing: 2 Bus. Days Intake Processing/Routing: 2 Bus. Days Intake Processing/Routing: 2 Bus. Days QC Review: 3 Bus. Days 1st Submission: 10 Bus. Days 1st Submission: 5 Bus. Days Intake 1st Submisson: 2 Bus. Days 1st Submission (Family land transfer and Res. Deed of Consolitdation): 20 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission: 15 Bus. Days Plats/Simple/Resub./Consol. Intake QC Processing: 2 Bus. Days QC Review: 3 Bus. Days Intake 1st Submisson: 2 Bus. Days 1st Submission Routing: 2 Bus. Days 1st Submission: 12 Bus. Days Intake 2nd Submisson: 2 Bus. Days 2nd Submission: 8 Bus. Days